The foreign footprint
Every project since 2008 worth US$25 million or more, or strategic at any size, that India, China or the Gulf has funded, financed or invested in: 32 in all, finished or not. Checked against the latest reports on 19 November 2026.
Shape: partner. Fill: status. Area: value, where disclosed (smallest size: value not disclosed). Where markers crowd, they are moved apart and a thin line points to the true site. Hover over a marker for details. Outlines: geoBoundaries (OpenStreetMap); recent reclamation may not be shown.
All 32 projects
| India · 12 projects | |||
|---|---|---|---|
| 1 | Hanimaadhoo airportHanimaadhoo International Airport. Exim Bank of India credit line; built by JMC Projects (India), US$136.6m. Inaugurated 9 Nov 2025. | US$137m | Completed |
| 2 | Addu reclamationAddu reclamation (184 ha) and shore protection. Exim Bank of India credit line, US$80m. Handed over 11 Aug 2024. | US$80m | Completed |
| 3 | Addu roads and drainageAddu City roads and drainage: 111 km of roads, 106 km of drainage and a 1.4 km detour link road with two bridges. Exim Bank of India credit line; built by Afcons (India); contract about MVR 1.2bn. Detour road opened Aug 2024; project inaugurated Jul 2025. | US$78m | Completed |
| 4 | Police collegeNational College for Policing and Law Enforcement, Addu. Indian grant, reported at US$33m, then India's largest grant project in the Maldives. Inaugurated 27 Mar 2022. | US$33m | Completed |
| 5 | Gan airportGan International Airport expansion. Exim Bank of India credit line; Renaatus Projects (India), US$29.7m contract signed Mar 2023. | US$30m | Under way |
| 8 | Thilamalé BridgeThilamalé Bridge (Greater Malé Connectivity Project), 6.7 km. India: US$400m Exim Bank credit line and US$100m grant; built by Afcons (India). About 76% complete by mid-2026; link to Thilafushi targeted by end-2027. | US$500m | Under way |
| 13 | 4,000 flats4,000 social housing units, Hulhumalé Phase 2. Exim Bank of India buyer's credit, US$227m; built by NBCC and JMC/KPIL (India). 700 handed over Oct 2024; keys to 3,300 handed over Jul 2025. | US$227m | Completed |
| 21 | Hulhumalé roadsRoads in Hulhumalé Phases 1 and 2. Exim Bank of India buyer's credit, about US$53m; built by Mohan Mutha–Ashoka Buildcon (India). | US$53m | Completed |
| 26 | Defence Ministry buildingNew Ministry of Defence building, Malé. Indian grant; value not disclosed. Inaugurated by Modi and Muizzu, 25 Jul 2025. | Not disclosed | Completed |
| 29 | UTF coastguard harbour (not pinned)Coast Guard Ekatha Harbour, Uthuru Thila Falhu, North Malé Atoll. Indian grant aid; built by Rail Vikas Nigam (India); value not disclosed. Under construction; completion not yet announced. Exact site not mapped. | Not disclosed | Under way |
| 30 | Water and sewerage, 28 islands (several sites)Water supply on 22 islands, sewerage on 2 and both on 4, across the atolls. Exim Bank of India credit line, about US$110m. Handed over 10 Aug 2024. | US$110m | Completed |
| 32 | Coastal radar system (several sites)Coastal surveillance radar network for the MNDF, with Indian assistance. Inaugurated Jun 2019. Several sites. | Not disclosed | Completed |
| China · 14 projects | |||
| 6 | Addu Link Road upgradeAddu Link Road redevelopment: 12.3 km from the Detour Bridge to Hithadhoo Stadium, widened from two to four lanes. Rotime Engineering and Technology (China), contractor-financed, reported at MVR 446.1m. Signed 24 Sep 2026; replaces a 2025 contract with the state Road Development Corporation. | US$29m | Signed, not started |
| 10 | Velana runwayNew runway, fuel farm and cargo complex at Velana. Exim Bank of China, US$373.8m; built by Beijing Urban Construction Group. US$74.7m refinanced in 2024. | US$374m | Completed |
| 11 | 7,000 flats7,000 flats, Hulhumalé Phase 2. Built by China State Construction Engineering; ICBC loan to HDC, US$368.9m (2017), government-guaranteed. | US$369m | Completed |
| 12 | Thilafushi portNew commercial port replacing Malé port. Phase one awarded to China Harbour Engineering Company (CHEC) in Feb 2026; about US$250m total project; all services to move by 11 Nov 2027. Previously planned at Gulhifalhu with Indian financing. | US$250m | Under way |
| 14 | Friendship BridgeChina–Maldives Friendship Bridge (Sinamalé). US$210m contract: Chinese grant of about US$126m plus an Exim Bank of China loan. Opened Aug 2018. | US$210m | Completed |
| 15 | Vinares flatsVinares housing, about 1,530 units, Hulhumalé. China Development Bank loan to HDC, US$159m (2017); built by CMEC. Completed Jul 2022. | US$159m | Completed |
| 16 | 1,500 flats1,500 housing units: 704 in Hulhumalé, the rest in Addu, Fuvahmulah and Gaafu atolls. Exim Bank of China concessional loan, RMB 982.5m (2012); built by CMEC. Handed over Dec 2017. | US$156m | Completed |
| 17 | Vilimalé hospitalChina–Maldives Friendship Hospital, 112 beds. Part of an RMB 600m (about US$84m) Chinese grant that also covers Malé–Vilimalé roads and 50 island council buildings. Implementation agreement signed 19 Jan 2026; contractor to be tendered. | US$84m | Signed, not started |
| 18 | Hulhumalé power plantSTELCO 5th Power Development Project: 50 MW power plant and desalination, Hulhumalé. Buyer's credit from China Eximbank and Bank of China, about US$75–80m (2015); built by Dongfang Electric. Completed Jul 2019. | US$80m | Completed |
| 20 | 1,000 flats1,000 housing units, Hulhumalé. Exim Bank of China concessional loan, RMB 481m (2010); built by China Machinery Engineering Corporation. Handed over Dec 2012. | US$73m | Completed |
| 22 | Seaplane terminalSeaplane facilities at Velana. China Development Bank loan, US$47.2m (2018); built by Beijing Urban Construction Group. Opened 17 Nov 2019. | US$47m | Completed |
| 23 | Hulhulé–Hulhumalé link roadLink road joining the airport island to Hulhumalé. ICBC loan to HDC, US$31m (2017); built by Hunan Construction Engineering Group. Completed 2018–19. | US$31m | Completed |
| 25 | Gulhifalhu roadsGulhifalhu roads and municipal infrastructure. China Machinery Engineering Corporation, contractor-financed. Contract signed 6 Jan 2025; value not disclosed. | Not disclosed | Under way |
| 27 | MNDF buildingIntegrated Accommodation and Logistics Building, 15 storeys, for the MNDF at Kalhuthukkalaa Koshi, Malé. Rotime Engineering and Technology (China), design and build; value not disclosed. Signed Nov 2026; two years to complete. | Not disclosed | Signed, not started |
| Gulf · 6 projects | |||
| 7 | Ihavandhippolhu portMaldives Economic Gateway: international port and economic hub. SERH Group (Abu Dhabi) with STO. Tripartite agreement signed 16 Nov 2026; value not disclosed. | Not disclosed | Signed, not started |
| 9 | Velana passenger terminalNew passenger terminal. Loans from Saudi Fund (US$217m), Kuwait Fund (US$100m), Abu Dhabi Fund (US$90m) and OPEC Fund (US$50m). Saudi Binladin Group, construction subcontracted to CHEC. Opened 26 Jul 2025. | US$457m | Completed |
| 19 | Hulhumalé bridges and channelsHulhumalé Phase 2 bridges, channels, sheet piling and coastal protection. Saudi Fund for Development loan, SAR 300m (about US$80m, 2015). Bridges inaugurated May 2024. | US$80m | Completed |
| 24 | 400 flats (Saudi)400 affordable flats, Hulhumalé Phase 2. Saudi Fund for Development, US$25m. Work launched 2026. | US$25m | Under way |
| 28 | Ras Malé waterfront (not pinned)Maldives Waterfront and Marina, Ras Malé (Fushidhiggaru lagoon, South Malé Atoll, near Gulhi, about 17 minutes by boat south of Malé). Eagle Hills (Abu Dhabi), private investment. Up to US$12bn envisioned, not committed. Commercial terms signed 21 Sep 2026. | US$12bn envisioned | Signed, not started |
| 31 | Health sector development (several sites)Saudi Fund for Development loan, US$50m, signed May 2024. Several sites. | US$50m | Signed, not started |
What it shows
Analysis
Everything in one bay. Twenty of the 32 projects sit in Greater Malé, eleven of them on Hulhumalé and the airport island alone. The airport has a Gulf-funded terminal beside a runway and seaplane base built with Chinese loans, reached by a Chinese bridge. India's Thilamalé Bridge will link Malé to the Chinese-built roads on Gulhifalhu and to a port at Thilafushi now being built by a Chinese contractor. No partner can withdraw without leaving something half-connected, which raises the cost of exit for all of them.
Three eras of money. China's footprint is mostly finished and mostly debt: flats, power and the airport, built on loans signed between 2010 and 2018, the bulk under Yameen. India's is mostly from the Solih years, through the 2019 credit line and buyer's credit: Addu, Hulhumalé, Hanimaadhoo and the Thilamalé Bridge, plus grant-funded security buildings. Under Muizzu the new work is mixed: Chinese contractors win roads, a port and a military building, often on contractor finance; Gulf money moves from development loans to land and ports.
Addu is a microcosm. In the far south India reclaimed land, built the city's roads, a police college and is expanding the airport. A Chinese firm is now widening the main Link Road beside India's detour bridge.
The north is the new frontier. India's Hanimaadhoo airport and the Gulf port at Ihavandhippolhu are both in the far north, close to the Eight Degree Channel. Whoever builds there sits beside the main shipping lane and a short distance from Indian territory at Minicoy. See India, China and Gulf capital and Ras Malé.